I-64 Peninsula Widening Segment 2

Segment 2             

Newport News, York County and James City County

Segment 2 is a 7.08-mile corridor of I-64 that continues westward from the Segment I construction improvements to a six-lane interstate system from 1.05 miles west of Route 199 (Humelsine Parkway/Marquis Center Parkway) near exit 242 to where the Segment I project ends, 0.54 miles east of Route 238 (Yorktown Road) near exit 247. The widening is expected to occur in the median of the existing interstate, limiting the amount of right of way required to construct the project and avoid impacts to existing interchanges. Segment II construction began on October 26, 2016.

Map of Segment II

At a Glance        

Construction estimated to begin: Fall 2016
Estimated completion: Summer 2019
Cost: $213.6 million
Project limits: From 1.05 miles west of Route 199 (exit 242) to 0.54 miles east of Route 238 (exit 247)
Contractor: Allan Myers, VA Inc.

Schedule

Final EIS approved:  November 2013
RFQ:  April 21, 2015
Design public hearing: April 30, 2015
FHWA record of decision:  Summer 2015
Request for proposal: July 21, 2015
Award design-build contract: January 20, 2016
Start: Fall 2016