Our Major Milestones to Date
July 2017
Chief Information Officers (CIOs) from across the region began discussing a regional broadband concept.
Fall 2017
The City of Virginia Beach announced completed construction on the first transatlantic cable (Marea).
Fall 2017
HRPDC endorsed the Three-Phased Regional Fiber Ring Plan submitted to Go Virginia.
Early 2018
Hampton Roads City Managers charged their CIOs to identify how regional connectivity can benefit public safety, higher education, and economic development
July 2018
Five Hampton Roads Southside cities formed the Broadband Steering Committee.
October 2018
The region won National Smart Infrastructure Challenge.
January 2019
Completed 30% of the design and Master Plan for the Regional Fiber Ring.
November 2019
Southside Network Authority was formed.
June 2020
Hired Interim Executive Director and Hired Columbia Telecomm Corp (CTC) to conduct 60% of design and develop a construction cost estimate and business case analysis.
Mid-November 2020
CTC delivered 60% design, estimated construction cost, and business case analyses on options and timelines.
Mid-December 2020
Held a strategic retreat to examine the business case, estimated construction cost, and 60% design.
November 2021
Made the decision on the optimal approach for fiber infrastructure financing, construction, and ownership, including potential private partnerships.
2022 to 2025
Construction of Southside Regional Fiber Ring is ongoing.
Our Work Ahead
Major Milestones for the future:
2026
Lower cost, faster service, and broader coverage delivered to 757 Southside residents, businesses, and educational institutions.